DEMOLITION PROCESS AND TIMETABLE

We make the demolition process as simple as possible.
As a “rule of thumb” we recommend our clients allow six (6) weeks from acceptance of a quotation to a cleared site.

Online Demolition |Demolition and Excavation Experts Melbourne | Melbourne and Mornington Peninsula

HELP PROVIDED AT EVERY STEP

Every demolition is unique and we have the valuable knowledge, experience and expertise to assist our clients in the event of more complex situations which may include:

  • Easements
  • Shared Services
  • Tree Permits
  • Protection Works Notices
  • Adjoining Property Requirements
  • Traffic Management
  • Steep Blocks

Quotation

Contact us for a FREE 'no obligation' quotation.

Read more...

STEP ONE: QUOTATION

Online Demolition can be contacted on (03) 9855 0030.

Demolition Permit

Generally allow three (3) weeks for
a demolition permit.

Read more..

STEP TWO: DEMOLITION PERMIT

All quotations include Demolition permits and Online Demolition proactively work together with the relevant Building Surveyors to ensure permit applications are processed in a timely manner.

Services Abolishments

Both Gas and Power services are required to be
abolished prior to commencement of demolition.

Read more...

STEP THREE: SERVICES ABOLISHMENTS

Abolishments can only be undertaken by your service provider however Online Demolition are keen and willing to assist all Clients with the process.

Temporary Fencing

Quotations include the supply and installation of
temporary fencing for a maximum of three months.

Read more...

STEP FOUR: TEMPORARY FENCING

The duration of temporary fencing can be extended if required.

Asbestos Removal

Asbestos Removal is undertaken by fully registered Asbestos Removers.

Read more...

STEP FIVE: ASBESTOS REMOVAL

All asbestos is removed in accordance with 2007 OH & S regulations.

Manual Demolition

Removal of salvage and recyclables.

Read more..

STEP SIX: MANUAL DEMOLITION

Manual demolition is undertaken to prepare the site for safe mechanical demolition.

Demolition/Site Clearing

Final stage of demolition by a 20 tonne excavater.

Read more...

STEP SEVEN: DEMOLITION/SITE CLEARING

This stage removes all demolition recyclables an waste from site by semi tippers.

Final Certificate

The site is inspected by the relevant Building Surveyor
and a Certificate of Final Inspection is issued.

Read more...

STEP EIGHT: FINAL CERTIFICATE

That's it! The process has been completed.

  • Quotation

    Contact us for a FREE ‘no obligation’ quote. Online Demolition can be contacted on (03) 9855 0030.

  • Demolition Permit

    Generally allow three (3) weeks for a demolition permit. All quotations include Demolition permits and Online Demolition proactively work together with the relevant Building Surveyors to ensure permit applications are processed in a timely manner.

  • Service Abolishments

    Both Gas and Power services are required to be abolished prior to commencement of demolition. Abolishments can only be undertaken by your service provider however Online Demolition are keen and willing to assist all Clients with the process.

  • Temporary Fencing

    Quotations include the supply and installation of temporary fencing for a maximum of three months. The duration of temporary fencing can be extended if required.

  • Asbestos Removal

    Asbestos Removal is undertaken by fully registered Asbestos Removers.

  • Manual Demolition

    Removal of salvage and recycling and preparation of site for safe mechanical demolition.

  • Demolition/ Site Clearing

    Final stage of demolition by a 20 tonne excavator. This stage also requires removal of rubbish and debris from site by semi tippers.

  • Final Certificate

    The site is inspected by the relevant Building Surveyor and a Certificate of Final Inspection is issued.